This page lists the outputs and deliverables produced by the ACRID project

Outputs that are identified as formal project deliverables are given in the table below. Other ad-hoc outputs are given here.

Project deliverables

Workpackage Deliverable Target date Output / Outcome
1 D1.1 Detailed project plan, work plan, budget; consortium agreement 15-Dec-2010 Documents delivered to programme manager, Dec 2010
D1.2 Initial project website 1-Oct-2010 Website established, 6 Sep 2010
D1.3 Mid-term report 1-Mar-2011 Report delivered to programme manager, Mar 2011
D1.4 Final project/budget reports 31-Jul-2011 -
2 D2.1 Description of scientific workflows 1-Mar-2011 Report delivered to programme manager, Mar 2011
D2.2 Information architecture 1-Mar-2011 Report delivered to programme manager, Mar 2011
3 D3.1 Deployed tools for managing climate research software 1-Jun-2011 -
D3.2 Deployed tools for managing climate research data 1-Jun-2011 -
4 D4.1 RDF-based climate research data model 1-Apr-2011 -
D4.2 Deployed linked-data server 1-Jul-2011 -
D4.3 Software for rendering data in different forms 1-Jul-2011 -
D4.4 Citation infrastructure 1-Aug-2011 -
5 D5.1 CRUTEM dataset exposed 1-Aug-2011 -
D5.2 CRU TS dataset exposed 1-Aug-2011 -
D5.3 Tree-ring data exposed 1-Aug-2011 -
D5.2 HadCET dataset exposed 1-Aug-2011 -
6 - There are no deliverables associated with WP6 - -